This morning at 5:30am, the dedicated teams of SupErb Construction, Triple T Excavating and Island Paving began the ambitious task of paving the entire main circuit of the track in one day.  We’re now 4 hours in and are already a head of schedule by paving an average of 4 meters per minute.  It’s been amazing to see the teams at work and we will continue to add photos throughout the day to show you the progress.
 