With the road course paving now complete, Shoes Line Painting have spent the last week at the Circuit completing the kerbs and lines on the track. What a difference the track lines, the painted kerbs and the painted verges have made.
Triple T Excavating
Ladies and gentlemen, as of 3:08 pm today, Friday March 18, 2016 the main road…
With only 11 weeks to go until the soft opening of the Circuit, along with the growing season upon us, the focus has once again shifted to the exterior of the facility.
With an average temperature of 15 degrees this week, it’s evident why Vancouver Island has…
Some people want it to happen, some wish it would happen, others make it happen. On October 27th, we made it one step closer to making this vision of the Motorsport Circuit happen.
This morning at 5:30am, the dedicated teams of SupErb Construction, Triple T Excavating and Island Paving began the ambitious task of paving the entire main circuit of the track in one day.